AEP Reynolds –
Meadow Lake Rebuild

This 20-mile rebuild in western Indiana replaced a 1950s vintage double-circuit 345-kV tower line with a higher capacity, higher efficiency double-circuit BOLD 345kV lattice tower.

AEP Reynolds – Meadow Lake Rebuild

Approximately nine miles of AEP’s 1950’s era double-circuit 345-kV lattice tower line western Indiana has been replaced with a higher capacity, higher efficiency double-circuit 345-kV lattice tower line.

Construction began in fall 2016 and is now complete, with the towers being placed within the same footprint to avoid impacting agricultural operations and the community.

Energized: Summer 2017